Alright, here’s
another entry of catching up.
Right after
excavation on September 20, we received some rain, but this didn’t really delay
things. Our foundation footings were poured before we visited the site on the
25th. I’ve read other Ryan Home builders comment that looking at the
footings makes the house seem smaller than it actually is. Because it was so
muddy, we didn’t walk around the space, so here’s a nice shot from the front.
You can see the
sump pump location and some draining stuff. The large mound of dirt will be our
garage. The piles of dirt around the space were huge. Since there’s so little
room on the street now, I guess they were forced to pile it up.
After the footings
were poured, we received another, larger batch of rain which did delay things
several days. Despite the weather, they were able to get the basement walls poured
as things dried up later in the week (the 28th) Our PM sent us the
photo below.
We did visit the
site over the weekend to see things in person. Things were still significantly
muddy, so again, here’s a photo from the front, driveway area.
Now we’re really
caught up on progress. We swung by our lot again on October 3. There were still
people working at our site, so we let them be and simply walked by on our
neighbor’s sidewalk. Said neighbor’s house appears to be complete as they
received their fully sodded yard and all poured concrete. A nice surprise was
the pile of lumber behind our basement walls. Hopefully this means things will
really start moving soon (and that the pile won’t be stacked and exposed to the
elements for too long).
We received our
regular weekly update from our PM on Friday, October 5, along with this photo.
According to his
email, our home was back filled, and the under-slab plumbing was installed along
with the basement steel. He indicated that the next week (this week) they would
pour the basement and garage slabs. Yay!
Estimated completion: Mid- to late-December, around 83 days
No comments:
Post a Comment