Timeline


  7/07/18 – Visited Ryan Homes with our Realtor
                     Met our Sales Representative
  7/08/18 – Placed hold on our desired lot
  7/13/18 – Signed purchase agreement 
                     Selected design package
                     Confirmed initial upgrade choices
  7/19/18 – Applied for NVR mortgage
  7/23/18 – Guardian meeting
  7/27/18 – Signed off on Guardian selections
  8/06/18 – Mortgage Approved
  9/07/18 – Pre-Construction meeting with Sales Rep and Project Manager
  9/12/18 – Considering different mortgage lenders and FHA vs Conventional
  9/17/18  Lot staked
  9/20/18  Groundbreaking
                     Compared lenders and proceeding with conventional loan
  9/25/18  Footings poured
  9/28/18  Basement walls poured
                     Locked 90-day mortgage rate with NVR
10/02/18 – external waterproofing installed
10/03/18  ~ lumber delivered, basement steel installed
10/05/18  ~ house backfilled, under-slab plumbing installed
10/12/18 – Exterior framing completed, interior framing in progress
10/19/18 – finished framing, started roofing, heating, electric, and plumbing
10/24/18 – Inspections are done
10/25/18 – Pre-drywall Meeting
10/26/18 – Insulated completed
11/09/18 – Drywall completed and first coat of paint, started flooring
11/16/18  installed trim and completed electric and plumbing finishes