November 29, 2018

Big Changes Inside and Out

After our pre-drywall meeting on Oct. 25, we received our usual update from our PM. He shared that the house passed all inspections (we knew this because all inspections must be passed before the pre-drywall meeting), and insulation began. In the photos below, you can see the drywall laying in the house. This was being delivered when we met with our PM.

November 18, 2018

Pre-Drywall Meeting

Inspections were completed at the beginning of week 5 of construction, and we were ready for our pre-drywall meeting by Thursday, Oct. 25. This was an opportunity to meet with our PM and discuss any questions or concerns we have so far in the process. We walked through the house and looked at every detail we could. Below are a handful of photos I took along the way.

November 15, 2018

And There's a House!

Ok, this is just ridiculous now… Going all the way back to the second week of October (one month ago!), the house was just basement walls. Since then, a lot of things have happened. When others have written that this process moves quickly, they were not kidding.